Cable capacity emerges as bottleneck for AI data centres, Nexans says

Oct 22 : Cable production capacity is emerging as a bottleneck for AI-driven data centre construction, Nexans’ finance chief said, as demand rises faster than the industry’s ability to expand manufacturing capacity.Global cable capacity is tight and building a new cross-linked polyethylene (XLPE) cable produc


Business

Cable capacity emerges as bottleneck for AI data centres, Nexans says

Cable capacity emerges as bottleneck for AI data centres, Nexans says

FILE PHOTO: A technician works at an Amazon Web Services AI data center in New Carlisle, Indiana, U.S., October 2, 2025. REUTERS/Noah Berger for AWS/File Photo

Read a summary of this article on FAST.

Get bite-sized news via a new
cards interface. Give it a try.

Click here to return to FAST
Tap here to return to FAST

FAST

Oct 22 : Cable production capacity is emerging as a bottleneck for AI-driven data centre construction, Nexans’ finance chief said, as demand rises faster than the industry’s ability to expand manufacturing capacity.

Global cable capacity is tight and building a new cross-linked polyethylene (XLPE) cable production line, known in the industry as a CV line, takes around three years, limiting how quickly suppliers can respond to demand, Nexans CFO Vincent Piquet told Reuters.

“Things can’t move quickly and the people building these data centres are in a great hurry,” Piquet said.

Data centres require large amounts of low- and medium-voltage cable to connect power infrastructure, with larger facilities consuming proportionately more medium-voltage cable.

Guess Word

Guess Word
Crack the word, one row at a time


Buzzword

Buzzword
Create words using the given letters


Mini Sudoku

Mini Sudoku
Tiny puzzle, mighty brain teaser


Mini Crossword

Mini Crossword
Small grid, big challenge


Word Search

Word Search
Spot as many words as you can


Show More


Show Less

The strain on power infrastructure is already delaying some projects. In September, Oracle issued a force majeure notice to a Blue Owl unit developing a large data centre in New Mexico, citing potential difficulties securing sufficient power for the site.

Piquet said grid constraints, while slowing some projects, were also supporting demand for Nexans’ products and allowing the company to be more selective when allocating capacity.

French distribution network operator Enedis has moved from annual procurement agreements to contracts lasting six or seven years in order to secure cable supply, he said.

While Europe generally faces fewer grid-connection challenges than the United States and benefits from stronger electricity networks in some northern countries, Piquet said lengthy regulatory processes were delaying certain projects.

He said he did not expect demand linked to artificial intelligence to slow, although Europe’s data-centre expansion was likely to be less pronounced than in the United States because private investment capacity was smaller and public funding played a larger role.

Source: Reuters

Sign up for our newsletters

Get our pick of top stories and thought-provoking articles in your inbox

Inbox

Get the CNA app

Stay updated with notifications for breaking news and our best stories

Get WhatsApp alerts

Join our channel for the top reads for the day on your preferred chat app

Whatsapp

Get bite-sized news via a new
cards interface. Give it a try.

Click here to return to FAST
Tap here to return to FAST

FAST

Leave a Reply

Your email address will not be published. Required fields are marked *

About the Author

Easy WordPress Websites Builder: Versatile Demos for Blogs, News, eCommerce and More – One-Click Import, No Coding! 1000+ Ready-made Templates for Stunning Newspaper, Magazine, Blog, and Publishing Websites.

BlockSpare — News, Magazine and Blog Addons for (Gutenberg) Block Editor

Search the Archives

Access over the years of investigative journalism and breaking reports